Signalling function control Brattøra Trondheim station

Installation check out and function control of the NSI-63 relay interlocking for Trondheim station. The work was done by personnel certified by Jernbaneverket as “Sluttkontrollør F” during several phases of the project NAV Brattøra.

Function control signalling Dilling-Fredrikstad.

Function control of the signalling systems of Østfoldbanen Dilling-Fredrikstad; after rebuild due to planned ballast cleaning. The installation and commissioning was done in several phases. Scope of the rebuild included new cables; track fields and outdoor cabinets for Dilling; Råde and Onsøy stations and adjacent line block sections. Also included function control of a point machine at Drammen station.

Function control CTC Ofotbanen

Function control of NSI-63 relay interlockings during installation of new Centralized Train Control system for the Ofotbanen line. Included installation check-out and was done in several phases by personnel certified by Jernbaneverket as “Sluttkontrollør F”.

Test and commissioning of level crossing signals; Ganddal freigth terminal

The assignment scope was post installation check out; test and commissioning of level crossing signals for Orstad freight terminal. The installation work was done by other company in 2017. The activities were performed with personnel certified by Bane NOR as “Sikkerhetskontrollør signal” og “Sluttkontrollør F”.

Function control signalling; FATC Jessheim-Eidsvoll

The overall project scope was to rebuild the signalling system on 5 stations on the Hovedbanen line; and modify the ATC system from DATC to FATC on the entire section of the line. ProRail AS scope was quality audit of the signalling contractor; site management and error correction during a 10 day shutdown of the line and complete function control of the 5 NSI-63 relay interlockings/ATP-system and adjacent line block sections. The work was done by personnel certified by Bane NOR as “Sluttkontrollør F”.

Function control; signalling Oslo S; RIV-RE Follobanen

The overall project scope was to modify eastern parts of the Oslo central station enabling building of the new Follobanen line. ProRail AS scope was to do function control on the affected trackside signalling objects for the NSB-77 relay interlocking. The work was done by personnel certified by Bane NOR as “Sluttkontrollør F” during summer shutdowns.