Function control signalling; FATC Jessheim-Eidsvoll

Function control signalling; FATC Jessheim-Eidsvoll

The overall project scope was to rebuild the signalling system on 5 stations on the Hovedbanen line; and modify the ATC system from DATC to FATC on the entire section of the line. ProRail AS scope was quality audit of the signalling contractor; site management and error correction during a 10 day shutdown of the line and complete function control of the 5 NSI-63 relay interlockings/ATP-system and adjacent line block sections. The work was done by personnel certified by Bane NOR as "Sluttkontrollør F".


Start date: 2016-09 - End date: 2016-12
 Client: Infranord Norge AS